Heaton Depot
The upgrade of Heaton Depot was required by Network Rail as part of the Intercity Express Programme (IEP) for the new fleet of Hitachi Super Express trains. The IEP programme involved the upgrade of 8 light maintenance depots on the East Coast Main Line, with works at each carried out in sequence to maintain the operational requirements of the ECML.
Client
Network Rail
Duration
8 months
Location
Heaton Depot, Newcastle
KEY STATISTICS
0
Accidents
48K
Hours Worked
100%
Depot Operation During Project
PROJECT SCOPE
• Construction of Temporary Fuelling Facility to cater for HST Tanking and Refuelling
• Construction of 2No attenuation slabs (1 x 15m, 1 x 93m)
• Installation of new Ad Blue Pumphouse, dispensers and associated pipeworks and Isolation Valves
• Installation of additional refuelling dispensers and associated pipeworks
• Installation of new 150mm, 300mm and 600mm drainage to allow drainage attenuation and additional manholes
• Installation of additional CET modules
• Renew P-Way
• Installation of GRP Track Collector pans (5 x 15m pans) and drainage